October 22, 2026
The flaggers working on Tiburon Boulevard this fall are the first stage of a Caltrans project that will repave all 4.6 miles from East Blithedale Avenue to the downtown roundabout. The new street layout stops well short of downtown. Bike lanes, protected bikeways and a new path run from Mill Valley to Blackfield Drive and end there. From Blackfield to Main Street, residents will get a smoother road with the same lanes they drive today, and that stretch isn't scheduled for more until 2029 at the earliest.
So the boulevard that comes out of this work in 2027 is really two roads. The rest of this post follows the corridor from west to east and explains why it splits where it does.
The project follows State Route 131, which is East Blithedale Avenue in Mill Valley and becomes Tiburon Boulevard east of the southbound Highway 101 on-ramp. According to Caltrans spokesperson Matt O'Donnell in The Ark, the work begins at the East Blithedale and Tower Drive intersection and ends at the downtown Tiburon roundabout, where Tiburon Boulevard turns into Paradise Drive.
Construction started the week of September 21. The City of Mill Valley's September 24 update said the first work is curb ramps and sidewalks, scheduled Monday through Friday from 7 a.m. to 5 p.m., with "limited traffic delays anticipated this fall." Caltrans' traffic advisory gives more detail:
Caltrans hasn't said which bus stops will be affected. The advisory says details for other intersections will come in future traffic advisories, and Mill Valley says Caltrans is working with Marin Transit and the local school district to limit the impact on bus routes. As of mid-October, the latest advisory on the Caltrans project page is dated September 16. That page is the best place to check before a weekday trip toward the freeway.
Drivers will notice the ramp work, but the change that matters most for daily trips comes later. Caltrans plans to pause construction over the winter, according to The Ark, and repaving is scheduled for spring 2027. A notice from the Mill Valley Chamber says the paving will happen overnight, from 11 p.m. to 6 a.m.
That schedule means the biggest single upgrade, a new surface from the 101 to Main Street, will mostly happen after the morning ferry crowd and dinner traffic downtown have gone home. Caltrans says the project is meant to improve ride quality and restore existing drainage systems on the corridor. In November 2025, The Ark listed the full scope as repaving, drainage, guardrails, curb ramps, signs, traffic signals, lighting, crosswalks and intersection improvements. The California Transportation Commission allocated $18.57 million, and Caltrans estimated construction would cost about $15.2 million.
The two sources give different finish dates. O'Donnell told The Ark in August 2026 that construction would last until July 2027. The Caltrans project page says completion is scheduled for "the winter of 2027." Both point to a boulevard that's under some kind of construction for most of next year.
The new street layout tapers off as you drive east. Caltrans splits the corridor into three segments:
The Ark's November 2025 report describes what that looks like on the ground. Class II bike lanes start on both sides at the Tower Drive and East Blithedale intersection and continue over the Highway 101 overpass. On Tiburon Boulevard they become Class IV protected bikeways at South Knoll Road and North Knoll Road, then end at Blackfield Drive. On the south side, a temporary Class I multiuse path will run between Strawberry Drive and Blackfield Drive, and The Ark reports a permanent path would follow in a later phase. Caltrans' own map describes the same layout, with a temporary two-way path on the inbound side between Strawberry and Blackfield.
The path ends where the existing Class III route along Greenwood Cove Drive and Greenwood Beach Road begins. The Ark notes that residents there have long raised concerns about bike traffic and have asked for faster cyclists to be moved out onto Tiburon Boulevard. Once the temporary path opens, more cyclists will arrive at Blackfield Drive with only the existing routes to continue on.
The lanes stop at Blackfield because of school buses. Caltrans first planned bike lanes from Blackfield Drive to Trestle Glen Boulevard, then reversed course after the Tiburon Peninsula Traffic Alliance, the Reed Union School District and the City of Belvedere raised concerns about school-bus service. The Ark reported that the Traffic Alliance, which runs the peninsula's school-bus program, identified four stops it said its bus provider would stop serving if the lanes went in. They were outbound at Jefferson Drive and inbound at the 76 gas station, Cecilia Way and Blackie's Pasture.
Once the lanes were taken out of the current project, the town stretch moved into a separate phase. As of The Ark's November 2025 report, Caltrans planned to build bike lanes inside Tiburon town limits as Phase 2, with funding to be secured in 2026 and construction targeted for early 2029. A stakeholder task force was supposed to help decide the bikeway and transit design. Caltrans, Marin County and Supervisor Stephanie Moulton-Peters were choosing a facilitator and planned to convene the group in early 2026. A February 2026 Transportation Authority of Marin project report says Phase 2 will add the permanent path, extend bikeways from Blackfield Drive to Trestle Glen and include bus stop improvements, and that it "will be programmed once all stakeholders have agreed on a finalized scope." That report doesn't set a new date, so early 2029 is still the most recent target with a date attached, and it now depends on that agreement.
The Town of Tiburon has its own related project. In the same report, town engineering manager David Eshoo described plans to install underground conduit for fiber-optic cable along the boulevard. He said that fiber could eventually connect the signals to systems that optimize timing, including AI-based ones. There's no published schedule yet for smarter signals on Tiburon Boulevard.
The Highway 101 end of the corridor is on the longest timeline. The Transportation Authority of Marin is studying long-term changes to the Tiburon Boulevard and East Blithedale Avenue interchange to ease congestion and improve safety. Mill Valley's update says TAM is still choosing consultants for environmental and engineering studies, and construction is not expected to begin before 2033.
Here is the full sequence by stage:
| Stage | Where | What changes | Timing |
|---|---|---|---|
| Phase 1 ramps and sidewalks | 101 interchange, moving east | 28 curb ramps, weekday flagging | Started week of Sept. 21, 2026 |
| Winter pause | Full corridor | Work stops | Winter 2026–27 |
| Phase 1 paving | Tower Drive to Main Street roundabout | New surface, 11 p.m. to 6 a.m. | Spring 2027 |
| Phase 1 bikeways | Tower Drive to Blackfield Drive | Class II and IV lanes, temporary path from Strawberry to Blackfield | Within Phase 1 |
| Phase 1 completion | Full corridor | Project closeout | July 2027 per The Ark, winter 2027 per Caltrans |
| Phase 2 | Blackfield Drive to Trestle Glen and in town | Bikeways and transit design | Last dated target early 2029, pending agreement on scope |
| TAM interchange | Tiburon Blvd and East Blithedale | Long-term interchange redesign | Not before 2033 |
Tiburon Boulevard is a state highway, so Caltrans is paying for its new surface. The town's own streets depend on a smaller budget. At an October 7 "State of the Pavement" presentation to the Town Council, Public Works Operations and Technology Manager Patrick Kerslake said Tiburon has about five years of restricted funding left for pavement projects. After that, keeping spending at current levels could take about $1.6 million a year from the general fund. The Ark quoted him calling it "a structural funding gap between the town's desired pavement investment and condition level, and the amount supported by recurring restricted transportation revenues."
Reedland Woods Way shows the town side of the problem. The Ark reports the street is set for repaving next summer, and a resident said town staff gave it a pavement-condition score of 41 out of 100. That puts it in the same season as the boulevard's final Phase 1 work. By summer 2027, a resident on a town street like that could have new pavement at both ends of the drive, while the stretch of boulevard between Blackfield Drive and Main Street keeps its current layout until Phase 2.
Road work is one of the details that comes up when Tiburon homes are priced and shown, from which weeks a showing route crosses a flagging zone to how a home near Blackfield Drive sits beside the new bikeways. If you're planning a sale around the 2027 construction calendar, The Sarkissian Bullock Team at Global Estates can walk through the timing with you. Request a Confidential Valuation.
Why People Are Making The Move In 2026
Why Smart Sellers List Now
A Parent’s Real Estate Guide
The Sarkissian Bullock Team is consistently regarded as the best and most trustworthy realty service found anywhere, offering their keen, personal advice to their clients.